Hidden costs of an IT implementation in SMEs: why a quote of 90k ends up as a 260k bill

· 8 min read · SilverData team

A quote for a new system implementation looks precise in an email. Licences: this much. Rollout: this much. Total: a specific number you can drop into the budget. The catch is that this number covers roughly half of what you'll actually spend over the first eighteen months.

This is not an article about vendors cheating you. Most of them don't cheat — they simply quote what they know how to quote, and everything else goes into the "it depends" box. "It depends" doesn't make it into the budget, so it doesn't exist. Until it does, no longer as a plan but as an invoice.

What you actually see in the quote

A standard implementation quote for an SME has three lines: licences (one-off or annual), implementation cost (person-days × rate × defined scope) and something like "post-go-live support" for the first 3–6 months. Everything looks tidy, the vendor can defend it in Excel, the client can approve it at the board.

The problem: this quote answers the question "how much does it cost to spin up the system in the version from the demo". It does not answer the question "how much does it cost to move the company onto it". And the company is not a demo database with 20 customers and 100 products — it is a dozen or more years of history, eight people who work differently from the textbook, and five other systems the new one has to start talking to.

Six categories the quote doesn't include

Nine out of ten implementations we pick up off the floor blew their budget for the same set of reasons. Worth knowing them up front.

A concrete example

A 30-person manufacturer of precast concrete elements from Silesia (prefabricated building parts, roughly 45 million PLN annual revenue) rolled out a new ERP in 2024 to replace a system more than a decade old. The vendor's quote: 90k PLN net (3-year licences + implementation, about 45 person-days). Deadline: 4 months. Everything looked good — until the rollout actually started.

The real bill after 14 months, when we took the project over, looked like this:

Total: 262k PLN, or 2.9× the base quote. Plus 10 months of slippage, and for half a year after go-live the company reported sales late because nobody fully trusted the numbers in the new ERP.

To be fair: this is not 100% the vendor's fault. The client also overestimated its readiness to change ("our people learn fast", "our data is in order", "we don't need modifications"). But if all these items had come up during the offer stage — the decision on the rollout would have looked different.

How to force an honest TCO

You don't have to be an implementation expert to ask questions the vendor has to answer in writing. A few specifics worth putting into the RFP:

A vendor who honestly answers these five questions will probably offer you a higher price up front. That is the good news — you are buying a plan, not a fantasy. A vendor who brushes them off ("that depends on you") or promises "we don't have those problems" has just disqualified themselves.

What next

Before you approve any quote on a system bigger than a few thousand euros, take a sheet of paper and write down the six categories from this piece. Add a realistic figure for your company next to each (a range is fine). The total you get at the bottom is your real TCO for the first 18 months — not the one in the quote.

If you want an outside look at a quote you've just received and the questions nobody has asked the vendor yet — we do these reviews for SMEs. The first call is free and takes half an hour.

An honest implementation quote is higher. But it is the only one you can keep.