Your IT project is going sideways: how to decide in two weeks whether to finish it, fix it or end the contract with your vendor

· 7 min read · SilverData team

The application was supposed to go live in May. It is November, you have paid two thirds of the price, and every meeting ends with "just the last few fixes". The demo looks good, but nobody has used the system for a single working day. The next invoice is waiting for approval.

This post lets you assess in two weeks what state the project is really in, and choose one of three ways forward: finish with the current vendor, cut scope and change the terms, or take over the code and switch vendors. The most common mistake we see is not a bad decision. It is no decision for another six months, because "we have already spent so much".

Five signs the project will not make it

One delay is normal. We typically see slippage of 20–30% on projects planned for 3–6 months. Worry when at least two of these show up.

  1. Two milestones in a row have slipped. If the first date moved by a month and the second by another two, the third will move as well.
  2. Demos only on test data. The vendor shows screens with sample customers but cannot run the system on a copy of your database from Comarch Optima, enova365 or Subiekt (the ERP and accounting systems most Polish SMEs run on).
  3. You have no access to the code. The code sits in the vendor's account, and when you ask for access you hear "we will hand it over after acceptance".
  4. The team keeps changing. The developer who started the project has left, and the new person has been "getting up to speed" for a month.
  5. Hourly invoices grow, the feature list does not. On time-and-materials billing you pay a similar amount every month, while the list of finished features has not changed in two months.

None of these signs means the vendor is dishonest. Often the project was underpriced, or the scope grew by half through your own requests. Check that honestly too.

Three ways forward and how to choose after a two-week review

Before you choose, run a review. It usually takes 2 calendar weeks and has four steps.

  1. Write down what you paid and what you got. A table: milestone from the contract, due date, amount paid, status today (works on production data / works in the demo / does not exist).
  2. Ask for the system to run on a copy of your data. One afternoon, your own person at the keyboard, the three most frequent operations from daily work. We described the same approach for user acceptance testing.
  3. Request access to the code repository and documentation. If the contract gives you the code rights, this is a reasonable request, not an accusation.
  4. Commission an independent code review. An outside developer estimates how much of the code is usable and how much work is left. Usually 3–8 working days and PLN 5,000–15,000 (about EUR 1,200–3,500).

Finish with the current vendor when the system works on your data for at least 70–80% of the scope, the team is the same, and less than 25% of the budget is left. Agree on a new, short schedule with one milestone every 2–3 weeks.

Fix the terms when the code is fine but the scope has drifted. Cut the scope down to the 3–5 features the system cannot launch without, move the code to your own repository and change the billing model. A common move is from fixed price to hourly billing with a cap.

Walk away and switch vendors when the review shows that more than half the code has to be rewritten, the team has fallen apart, or the vendor refuses access to the code. Every extra month then funds a project you will restart anyway.

A legal note for Polish contracts. If your contract is a contract for a specific work (umowa o dzieło), which is typical for fixed-price projects, the Polish Civil Code lets you withdraw before the deadline when the contractor is so late that finishing on time is unlikely (Art. 635), or at any time before the work is completed, in which case you pay the agreed fee minus what the contractor saved (Art. 644). Source: Polish Civil Code in ISAP. Hourly contracts usually have other termination rules. Read the contract with a lawyer before sending any letter.

Two cases from our projects

At one of our clients, a 26-person electrical wholesaler, a vendor was building a B2B ordering portal in .NET integrated with Comarch Optima. Fixed price PLN 140,000 (about EUR 33,000), planned for 6 months. In month eight the company had paid PLN 95,000 (about EUR 22,000) and the portal ran only on test data. The code review took 6 working days and cost PLN 9,000 (about EUR 2,100). Result: about 60% of the code was usable, and the Optima integration was missing.

The owner chose to fix the terms. Scope was cut to three features: customer login with their price list, placing an order, and order status from Optima. The code moved to the company's repository, and the rest was billed hourly with a cap of PLN 45,000 (about EUR 10,500). The portal went live after 7 weeks. The total came to PLN 149,000 (about EUR 35,000), PLN 9,000 more than the original price. After 3 months, 40% of regular customers' orders came in through the portal, and customer service saved about 10 hours a week of retyping orders from emails.

What we would do differently: repository access from day one and a demo on production data every month. The integration gap would have shown up in month three, not eight.

In another project, at a 40-person window manufacturer, a vendor was building a production planning application connected to enova365. Two milestones had already slipped by month five. The company kept paying for another 9 months, PLN 210,000 (about EUR 49,000) in total, because "we have already spent so much". Then the vendor's only developer left, and the code was not in the company's repository.

The new vendor needed 3 weeks just to get the project running on their side. About 60% of the code was thrown away. Finishing cost another PLN 120,000 (about EUR 28,000) and 5 months. The lesson: a decision in month five, at the second missed date, would have saved an estimated PLN 80,000 (about EUR 19,000) and half a year.

What walking away costs and what can go wrong

Switching vendors mid-project is almost never cheap. We typically see 4–8 weeks to take over the project, set up the environment and understand the code before the new team ships its first feature. The new vendor usually rewrites 30–60% of the code, even if the previous one was decent, because they prefer to be responsible for their own. Part of that is caution, part is self-interest.

Walking away also carries the cost of a dispute. If the vendor considers the withdrawal unjustified, you may receive a demand for payment for the rest of the contract. A withdrawal is easy to challenge when the delay is partly on your side: answers to questions after three weeks, scope changes in emails, no access to test data.

When walking away makes no sense: when less than 20% of the work is left and the only problem is a 4–6 week slip. Then it is cheaper to set a firm date and finish. It also makes no sense when you have neither the rights to the code nor a copy of it. Then the first step is negotiating a handover, not a termination. We described how in our IT vendor handoff checklist.

The code review can fail too. A developer from a competing firm who hopes to win the contract has a reason to judge the code harshly. Use a reviewer who will not continue the project.

What to do this week

An IT project rarely fails in a single day. It fails over the months in which nobody asked: what part of this works on our data. Ask it this week, and make the decision after a two-week review, not after another six months.